1. ACV Runway Improvements to Impact Commercial Air Service in August 2023

    The Humboldt County Department of Aviation will begin the Runway Rehabilitation and Electrical Improvement Project in June 2023 with anticipated completion in Dec. 2023. There will be no airline flights at ACV from Aug. 14-Aug. 25, 2023. Read on...
View All

Runway Rehabilitation and Electrical Improvement Project Schedule

  Date Closure Times Closure/Impacts
Phase I June 5 - Aug. 2 7 Day/Week
10 p.m. - 6 a.m.
Main Runway
(Runway 14/32)
Phase II      
A Aug. 14 - Aug. 25 All Day Entire Airport
B Aug. 28 - Sept. 1 and;
Sept. 4 - Sept. 8
Monday, Tuesday, 
Wednesday, and 
Thursday nights 
10 p.m. - 6 a.m.
Runway 14/32 and 
select connecting 
taxiways
Phase III Sept. 11 - Dec. 15 Monday - Friday 
every week
Midnight - 6 a.m.
Runway 14/32